How Much Concrete Do I Need for a Footing? Work It Out Before You Dig
A footing spreads the weight of a wall or column onto the soil. Get it too small and the structure settles; get the concrete maths wrong and the pour stops halfway down the trench.
The calculation is simple. You need three measurements: the total length of the footing, its width, and its depth.
The formula
Volume in cubic yards = Length (ft) × Width (ft) × Depth (ft) ÷ 27
Depth is usually given in inches, so convert it to feet first — 12 inches is 1 foot. The ÷ 27 step matters because there are 27 cubic feet in one cubic yard, and ready-mix concrete is sold by the cubic yard.
A worked example: a 20 ft footing, 2 ft wide, 12 in deep
- Volume: 20 × 2 × 1 = 40 cubic feet
- Cubic yards: 40 ÷ 27 = 1.48 cubic yards
Add 10% for waste — over-dig, an uneven trench bottom, and spillage — and you should order about 1.63 cubic yards.
Bagged concrete follows the same volume. An 80 lb bag yields about 0.60 cubic feet, so 40 cubic feet needs about 67 bags, or about 74 bags with the 10% waste allowance (always round bag counts up). The same pour needs about 89 × 60 lb bags, or about 134 × 40 lb bags, without waste.
If you would rather not do the arithmetic by hand, run the same numbers through a footing concrete calculator — it gives cubic yards, bag counts and cost in one step.
Two more common sizes
- 10 ft long, 2 ft wide, 12 in deep: 20 cubic feet → 0.74 cubic yards, about 0.81 with waste. About 34 × 80 lb bags, or 37 with waste.
- 30 ft long, 2 ft wide, 12 in deep: 60 cubic feet → 2.22 cubic yards, about 2.44 with waste. About 100 × 80 lb bags, or 110 with waste.
How wide and how deep?
For a single-storey wall, 2 ft wide by 12 in deep is standard. Wider footings suit heavier loads or soft soil. Depth should go below the local frost line in cold climates, or frost heave will lift the footing — 12 inches is a common minimum for garden walls and extensions.
Before you dig
- Measure the total trench length in feet.
- Decide the width — 2 ft is common for house walls.
- Decide the depth in inches and convert it to feet.
- Work out cubic yards, then add 10% waste, and round bag counts up.
Keep trench bottoms level, compact any soft spots before the pour, and add rebar lengthwise in structural footings for extra strength.